Burnside is well and nearing completion.
The entire building has been framed, windows have been installed, electrical has been run, plumbing has been installed, and we anticipate drywall being finished within the next few weeks. Naturally Covid-19 has forced a few minor delays, however we are persisting forward!
With the various Covid setbacks, our original completion date of January is now pushed to June 1, 2021.
Look below for all the latest updates!
Framing complete, windows installed, and drywall being prepared (taken 01/06/2021)


Framing underway (taken 10/24/2020)



Roofing nearing completion (taken 10/14/2020)-

Framing Progress (09/30/2020)-



Exterior Walls for the Second Floor



Pouring the Concrete
Pouring the concrete at Burnside